Skip to content
Home
Directory of Certified Individuals
Approved SPD-Sponsored Courses
Course Catalog
Basic Texas Purchaser
Certified Texas Contract Developer
Certified Texas Contract Manager
Continuing Education Webinars
Continuing Education Live Events
Ethics and Refresher Courses
New User Registration
Login
Contact Us
FAQ
Home
Directory of Certified Individuals
Approved SPD-Sponsored Courses
Course Catalog
Basic Texas Purchaser
Certified Texas Contract Developer
Certified Texas Contract Manager
Continuing Education Webinars
Continuing Education Live Events
Ethics and Refresher Courses
New User Registration
Login
Contact Us
FAQ
Project Management Overview Webinar and Quiz Quiz
Please sign up for the
course
before taking this quiz.
1.
What is a work breakdown structure?
A tool to estimate how long the efforts needed in a project will take.
A tool to determine which projects are a priority.
A tool to assign portions of a project to individuals.
None of the above.
2.
You should assign owners to action items in the project log to ensure they are completed.
True
False
3.
__________ collects risks, issues, actions, decisions, and assumptions to help keep a procurement on track.
Project Log
Solicitation
Needs Assessment
Planning Document
4.
Which of these statements is true about Risks and Issues?
A. A risk is something that might happen.
B. An issue is something that has happened.
C. Risks do not need to be monitored and have a way of working themselves out
D. Risks are easier to deal with than Issues.
E. A, B, and D
5.
How often should requestors or stakeholders be contacted when movement has slowed on the project?
Every 6 weeks.
Every 2 weeks.
Every 4 weeks.
Every week.